New expositions in the Museum Complex

People and Their Ancestors

In 2025, preparatory and implementation work continued on the anthropological and archaeological exhibition People and Their Ancestors. The exhibition contractor continued to prepare workshop documentation and detailed technical drawings. For the more technically and structurally demanding elements, the contractor built mock-ups at its warehouse to test structural and technological solutions as well as assembly methods. The test results were then incorporated into the final workshop documentation.

At the same time, logistical preparations were underway for the delivery of large glass elements, including tests of handling and installation methods in the exhibition halls. Installation of the exhibition in the halls subsequently began.

The specialist team continued to prepare texts, which were submitted for graphic design on an ongoing basis. Accompanying illustrations were also produced. The graphic treatment of the texts and illustrations was continually reviewed in relation to the proposed mounting and positioning of exhibits.

During the year, contracts were also awarded for the production of multimedia content and the supply of audiovisual equipment, followed by its installation and technical commissioning in the exhibition. Materials were prepared and multimedia content subsequently produced in cooperation with the specialist team.

As implementation progressed, exhibits were gradually transported from the National Museum’s depositories to the Museum Complex, where they were prepared for mounting and subsequent installation in showcases.

In 2025, the first part of the exhibition was completed and opened to the public. The opening was accompanied by an exhibition featuring the skeletal remains of Lucy and Selam, on loan from abroad.

For the remaining part of the exhibition, work continued on multimedia content, graphic design and mounting proposals as the workshop documentation was finalised.

The remaining part of the exhibition is scheduled to open in 2026.